Onward, Upward

There is a lot scheduled for the next week.  Some more excavation for the foundations of the bathrooms, placing the metal beams for the second floor, connecting the plumbing for the sewage/drainage systems.

The work has already started to prepare for the second floor.  The bar area of Terraplana will have a double high ceiling, so the forms for the second floor concrete need to be supported by a large structure.  The picture below shows the first part of the scaffold structure.


The pipes for the sewage/drainage system have also arrived.


That's about all we have to report this week.  The project appears to be basically on schedule.  If everything goes as planned, we should have construction finished in November.